Factory planning

Egg Tray Factory Requirements and Installation Readiness

Installation readiness begins with verified site data and a clear division between customer preparation and the contracted GDM scope.

Factory planning checklist

Confirm these interfaces before final engineering and quotation.

Civil works

  • Machine, dryer and pulper foundations
  • Drainage, access and lifting

Process systems

  • Pulp tanks and plumbing
  • Vacuum, compressed air and water

Energy

  • Electrical demand and panel interface
  • Dryer burner fuel line where applicable

Commissioning

  • Molds and raw material readiness
  • Customer technician, travel, visa and hotel responsibilities

Space, flow and access

The six standard models have a recommended production area of 150–200 m². Final layout must also consider raw-paper storage, finished-goods movement, dryer arrangement, maintenance access and local safety requirements.

  • 150 m²: ECPS-600E and ECPS-900E
  • 180 m²: ECPM-1200E and ECPM-1500E
  • 200 m²: ECPL-1800E and ECPL-2200E

Utilities to verify

Electrical supply must support model-specific maximum startup or peak demand of 65–200 kW. This is a power requirement, not average energy consumption. Compressed air, water make-up, drainage, ventilation and the approved dryer-fuel arrangement also need project confirmation.

  • Initial closed-loop water fill: 3–9 m³ by model
  • Process water is recycled; typical make-up is about 20% per month, mainly due to evaporation
  • Typical whole-line staffing: 2–3 or 3–4 workers per shift, depending on model

Responsibility split

The customer normally prepares a compliant building, foundations where required, utility connections, permits, lifting and site access. GDM supplies only the equipment and services stated in the project agreement.

Commissioning readiness checklist

Before the installation team arrives, confirm the project drawings for machine, dryer and pulper foundations; prepare the locations and interfaces for pulp tanks, plumbing, vacuum equipment and molds; have the approved burner fuel line prepared by qualified local contractors; and appoint a customer technician for commissioning and training. Travel, visa and hotel responsibilities vary by project and must be stated in the quotation or contract—not assumed.

Model30-egg trays/hourInitial water fillMaximum demandWorkers/shiftArea
ECPS-600E 600 3 m³ 65 kW 2–3 150 m²
ECPS-900E 900 4 m³ 75 kW 2–3 150 m²
ECPM-1200E 1,200 5 m³ 110 kW 2–3 180 m²
ECPM-1500E 1,500 6 m³ 140 kW 2–3 180 m²
ECPL-1800E 1,800 7 m³ 160 kW 3–4 200 m²
ECPL-2200E 2,200 9 m³ 200 kW 3–4 200 m²

Tell us about your production project

Send us your target product, capacity and site conditions. We respond with the line configuration that fits.

Request a quote